Question 41
MediumA and B together earn ₹6,000 for a job. A could do it in 12 days and B in 18 days. How much should B get?
- A.
Popular companies
Prepare company by company
Hiring pattern, syllabus, past questions and mocks for each company.
All companiesPractice by subject
Quantitative Aptitude
A and B together earn ₹6,000 for a job. A could do it in 12 days and B in 18 days. How much should B get?
₹2,400
₹3,600
₹2,000
₹3,000
Sign up free to see the answer and a step-by-step explanation.
4 men and 6 women finish a job in 8 days, and 3 men and 7 women finish it in 10 days. How long would 10 women take?
50 days
30 days
40 days
35 days
Sign up free to see the answer and a step-by-step explanation.
A can do a job in 20 days. He works for 5 days, and B finishes the rest in 18 days. How long would B alone take for the whole job?
36 days
30 days
24 days
20 days
Sign up free to see the answer and a step-by-step explanation.
A, B and C can do a job in 20, 30 and 60 days. A works every day, and B and C help him every third day. How long does the job take?
12 days
18 days
10 days
15 days
Sign up free to see the answer and a step-by-step explanation.
A does half as much work as B in three-fourths of the time. Together they take 18 days. How long would B alone take?
30 days
36 days
27 days
33 days
Sign up free to see the answer and a step-by-step explanation.
A can complete a job in 9 days. B is 50% more efficient than A. How long does B take?
7 days
4.5 days
6 days
13.5 days
Sign up free to see the answer and a step-by-step explanation.
If 6 men or 10 boys can finish a job in 15 days, how long will 3 men and 5 boys take?
15 days
30 days
10 days
20 days
Sign up free to see the answer and a step-by-step explanation.
A and B can do a job in 15 days. After working together for 6 days, B leaves and A finishes the rest in 30 days. How long would A alone take?
50 days
45 days
40 days
60 days
Sign up free to see the answer and a step-by-step explanation.
A can build a wall in 12 hours and B can break it down in 16 hours. If both work at once, how long will it take to build the wall?
36 hours
24 hours
28 hours
48 hours
Sign up free to see the answer and a step-by-step explanation.
40 workers can finish a road in 60 days. After 20 days, 10 workers leave. How many more days are needed to finish?
53⅓ days
50 days
40 days
45 days
Sign up free to see the answer and a step-by-step explanation.